NEW QUESTION # 31
Where do you control whether a project stock is managed as valuated or non-valuated project stock?
- A. In the WBS element
- B. In the material master
- C. In the project definition
- D. In the network activity
Answer: B
Explanation:
To control whether a project stock is managed as valuated or non-valuated project stock, you have to maintain the setting in the material master. The material master is a set of data that defines the characteristics and properties of a material that can be produced or procured. The material master contains various views that store different types of information about a material, such as basic data, sales data, purchasing data, accounting data, and so on. In the accounting view of the material master, you can specify whether a material is relevant for valuated project stock or not by using the Valuation category field. The valuation category is a parameter that determines how a material is valuated in different stock accounts. If you select Q as the valuation category for a material, it means that the material is relevant for valuated project stock and its value is updated in Financial Accounting. If you leave the valuation category blank for a material, it means that the material is relevant for non-valuated project stock and its value is not updated in Financial Accounting. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
NEW QUESTION # 32
How can you update the degree of processing for an activity?
- A. By using results analysis
- B. By confirming the activity
- C. By changing the activity
- D. By scheduling the activity
Answer: B
NEW QUESTION # 33
How are earliest dates and latest dates of activities scheduled?
- A. Earliest dates are scheduled by backward scheduling, and latest dates by copying the earliest dates
- B. Earliest dates are scheduled by forward scheduling, and latest dates by backward scheduling
- C. Earliest dates and latest dates are scheduled by forward scheduling
- D. Earliest dates are scheduled by backward scheduling, and latest dates by forward scheduling
Answer: B
Explanation:
Forward scheduling is a method of scheduling activities from the start date of the project to the end date. Backward scheduling is a method of scheduling activities from the end date of the project to the start date. The earliest dates are determined by forward scheduling and the latest dates are determined by backward scheduling. This ensures that the activities are scheduled within the project duration and that any slack time is distributed evenly. Reference: https://help.sap.com/viewer/0c9a2f8f9c1b4a2e8b3f7d0c9b6e1d8a/2020.000/en-US/4c5f7a3e6b571014e10000000a174cb4.html
NEW QUESTION # 34
Which sales documents can update planned revenues on WBS elements? Note: There are 2 correct answers to this question
- A. Sales order
- B. Quotation
- C. Billing
- D. Inquiry
Answer: A,C
Explanation:
Sales order and billing are some of the sales documents that can update planned revenues on WBS elements. Sales order is a document that records a customer's request for goods or services from a sales organization. Billing is a document that records the delivery of goods or services to a customer and requests payment for them. Both sales order and billing can update planned revenues on WBS elements if they are assigned to them directly or indirectly via network activities. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
NEW QUESTION # 35
For which objects can billing plans be created? Note: There are 2 correct Answers to this question.
- A. Sales order items
- B. WBS elements
- C. Project definition
- D. Milestones
Answer: A,B
NEW QUESTION # 36
You use a WBS project structure with network and maintenance order. You want to schedule both the network and the maintenance order .
What do you have to consider?
- A. The maintenance order s must be assigned to the same budget profile as the project definition.
- B. The maintenance orders must be assigned as sub-networks.
- C. The maintenance orders must be assigned to WBS element.
- D. The maintenance orders must be assigned to the same plant as the network.
Answer: C
Explanation:
To schedule both the network and the maintenance orders, you have to consider that the maintenance orders must be assigned to WBS elements. This means that you have to link the maintenance orders to WBS elements in your project structure using assignment objects. This way, you can ensure that the dates of the maintenance orders are synchronized with the dates of the WBS elements and the network activities. You can also use overall network scheduling to schedule several networks and maintenance orders together. Reference: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/4dd8cb7b1
NEW QUESTION # 37
An external component is assigned to a network activity. The delivery date for the purchase requisition depends on the dates of the network activity. What controls whether the delivery date is defined by the earliest or latest scheduled dates?
- A. The scheduling parameters for the network
- B. The table of MRP controllers
- C. The control key
- D. The network profile
Answer: A
NEW QUESTION # 38
Cost & budget
A service Company use project management and they complain that the system does not prevent their project manager from exceeding their budget.
What action do you have tsolve the problem?
- A. Activate availability control in the assign budget profile. Defined the tolerance limit in the customizing.
- B. Activate availability control for the important WBS element. Define the tolerance limit on each WBS element.
- C. Activate commitment
- D. Activate availability control For projects in the control area. Enter the plan data for each WBS element.
- E. management in the project definition. Enter the budget in the master data of the top WBS element.
Answer: A
Explanation:
According to SAP Help Portal3, "You can use availability control to monitor budgets for projects or parts of projects (WBS elements). Availability control checks whether sufficient funds are available for planned or actual costs. If the budget is exceeded by a certain percentage (tolerance limit), the system issues a warning or an error message." Reference: 3
NEW QUESTION # 39
Resources
How can you define external task in your project.
Note : there are 2 correct answers for this question.
- A. Create a service activity in a network.
- B. Assign a purchase order for external processing to the project definition.
- C. Create a service milestone.
- D. Create an external activity in a network.
Answer: A,D
Explanation:
"You can create external activities in a network to represent tasks that are performed by external service providers or vendors." According to SAP Press4, "You can create service activities in a network to represent tasks that are performed by internal service providers." Reference: 4
NEW QUESTION # 40
Which sets of dates can be used to schedule networks? Note: There are 2 correct Answers to this question.
- A. Baseline dates
- B. Forecast dates
- C. Basic dates
- D. Planned dates
Answer: B,C
NEW QUESTION # 41
You want to determine the planned costs for an internally processed activity. Which data do you need Note: There are 2 correct answers to this question
- A. Duration
- B. Work
- C. Activity type
- D. Profit center
Answer: A,B
NEW QUESTION # 42
You are using budgeting and active availability control. How can availability control be activated? Note: There are 2 correct answers to this question
- A. Automatic activation with budget assignment
- B. Automatic activation with assignment to an investment program
- C. Automatic activation with the first actual posting
- D. Background activation (CJBV - Activate Availability Control) l
Answer: A,C
Explanation:
Availability control is a function that monitors whether the budget for a project is sufficient for planned and actual costs. Availability control can be activated in different ways depending on the settings in the availability control profile and the tolerance limits. Some of these ways are:
Automatic activation with budget assignment: Availability control is activated when you assign budget to a WBS element or a network activity.
Automatic activation with the first actual posting: Availability control is activated when you post the first actual cost to a WBS element or a network activity. Reference: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/4dd8cb7b1c484b4b93af84d00f60fdb8/79ceb65334
NEW QUESTION # 43
Materials
Your customer want to use scheduling for network to specify planned dates of task. In the SAP project system there are different set of dates that can be scheduled.
Which set of dates can be used for scheduled for network?
Note : there are 2 correct answer for this question.
- A. Fundamental dates
- B. Baseline dates
- C. Forecast dates
- D. Basic dates
- E. Planned dates
Answer: C,D
NEW QUESTION # 44
Resources
Which of the following transactions can you use to post actual cost for external processing.
Note : there are 2 correct answer for this question.
- A. Creating a service entry sheet
- B. Creating a purchase order.
- C. Posting a goods receipt
- D. Approval of a good receipt.
- E. Approval of a service entry sheet
Answer: D,E
Explanation:
The approval of a service entry sheet and the approval of a goods receipt are both transactions that can be used to post actual costs for external processing." Reference: 3
NEW QUESTION # 45
You use networks and internal activities in your project. You have activated capacity requirements and notice that one work center is overloaded. You have no authorization to change the work center. How can you reduce the overload of the work center? Note: There are 2 correct answers to this question
- A. Trigger automatic capacity leveling inside the project planning board
- B. Shift activities backward or forward on the time axis where more capacities are available
- C. Increase the capacities of the work center in the project planning board.
- D. Maintain subordinate internal activity elements assigned to other work centres
Answer: B,D
NEW QUESTION # 46
What functions are available for period end closing in SAP Project System? Note: There are 3 correct answers to this question
- A. Milestone trend analysis
- B. Progress analysis
- C. Settlement
- D. Confirmations
- E. Results analysis
Answer: B,C,E
Explanation:
Settlement, progress analysis, and results analysis are some of the functions available for period end closing in SAP Project System. Settlement is used to allocate the costs and revenues in projects or the results analysis data to one or more receivers, such as cost centers, profitability segments, or assets. Progress analysis is used to determine and compare the planned and actual project progress values, based on the overall planned costs and the work done. Results analysis is used to perform a periodic valuation of the project, based on the costs and revenues expected or incurred in the project. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
NEW QUESTION # 47
Which object is used to allocate the costs from a claim to the project structure?
- A. WBS element
- B. Claim
- C. Network activity
- D. Internal order
Answer: A
Explanation:
A WBS element is an object that is used to allocate the costs from a claim to the project structure. A claim is a document that records a customer's request for compensation due to deviations from the agreed terms and conditions of a project. A WBS element is a structural element of a project that represents a task or a partial task. You can assign claims to WBS elements and post costs or revenues to them. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
NEW QUESTION # 48
......
SAP S/4HANA project systems are a module of SAP S/4HANA that provides features and functionalities to manage project planning, execution, and monitoring. The SAP S/4HANA project systems module is designed to help organizations streamline their project management processes, reduce project costs, and increase project efficiency. The SAP C_TS412_2021 certification exam covers topics such as project structures, planning and budgeting, resource management, project execution, and project analysis and reporting.