NEW QUESTION 77
The desire of senior management to evolve your organization to be more responsive to changes in your marketplace or environment is best captured by which concept?

  • A. Increased collaboration
  • B. Business agility
  • C. Disciplined Agile
  • D. Guided continuous improvement (GCI)

Answer: D

 

NEW QUESTION 78
What is the definition of Disciplined Agile (DA)?

  • A. It is a process-decision tool kit that provides straightforward guidance to help people, teams, and organizations to streamline their processes in a context-sensitive matter.
  • B. It is a methodology that explores the various approaches to conducting agile and waterfall-based practices to project management.
  • C. It is an approach that frequently assesses the change within an organization to ensure all associated projects, programs, and portfolios are aligned
  • D. It is an agile set of practices that promotes autonomy within a project management office.

Answer: A

 

NEW QUESTION 79
A team working on a product grew from 8 to 12 team members. The Scrum master felt that they need to split into two scrum teams. After discussion, they decided to stick to one team as it was better for team cohesiveness and delivery. This is an example of:

  • A. Choice is good
  • B. Enterprise awareness
  • C. Being Awesome
  • D. Optimize for flow
  • E. Being pragmatic

Answer: E

 

NEW QUESTION 80
What is the main role of the team lead?

  • A. Ensure that the team builds the product right
  • B. Ensure that the team builds the right product
  • C. Coordinate the building of the product.
  • D. Build the product

Answer: C

 

NEW QUESTION 81
In Team Estimation...

  • A. You first estimate the relative sizes of all stories, then assign numbers to them.
  • B. Members of a group define what criteria will be used for determining the "Definition of Done".
  • C. You estimate what roles will be necessary in order to complete user stories.
  • D. Each team is ranked in order of importance for completing a task.

Answer: A

 

NEW QUESTION 82
Which of the following is NOT an important part of improving the WoW for a team?

  • A. Start where you are
  • B. Do the best you can
  • C. Always try to get better
  • D. Stick to a method once you discover it

Answer: D

 

NEW QUESTION 83
Which of the following is a TRUE statement in the context of roles in Disciplined Agile?

  • A. The Team lead helps the team discover the technical roadmap
  • B. The team members are expected to be highly specialized
  • C. The Product owner is the facilitator and process coach
  • D. A person may take on more than one role in a team

Answer: D

 

NEW QUESTION 84
What is the purpose of an Iteration retrospective?

  • A. To transfer knowledge and improvements to the next iteration.
  • B. To showcase what the team accomplished in an iteration.
  • C. To identify progress and to note encountered impediments.
  • D. To prioritize stories and concrete tasks for the next iteration.

Answer: A

 

NEW QUESTION 85
The primary purpose of creating a minimally viable product (MVP) is to:

  • A. Establish the validity of a hypothesis by putting a prototype in front of customers
  • B. Commit to continuous improvement by adding value
  • C. Finalize the product design through a series of experiments
  • D. Create a marketable product complete with useful features

Answer: A

 

NEW QUESTION 86
One of the differences between a MVP and a MBI is that:

  • A. MVP is a collection of MBI's
  • B. MBI is typically built incrementally on top of an existing product
  • C. MBI is the initial release that is sent to the customer
  • D. MVP represents a product that is released to the customer

Answer: B

 

NEW QUESTION 87
Using a Pull system for working does not mean:

  • A. Work content should keep in mind the team's capacity
  • B. WIP is kept at a reasonable level
  • C. Work is not pulled by the team unless they are ready
  • D. All team members are pulled in to to do the work

Answer: D

 

NEW QUESTION 88
Your organization wants to set up mechanisms so that teams can share their learnings with other teams. Which process blade is most likely to offer potential techniques to address this?

  • A. Portfolio Management
  • B. Support
  • C. Governance
  • D. Continuous Improvement

Answer: D

 

NEW QUESTION 89
The primary purpose of a community of practice is:

  • A. To bring all the experts in an organization together
  • B. To mentor, coach and guide others in a particular craft
  • C. To share knowledge among a group of like-minded people
  • D. To sell a particular competency to potential customers

Answer: C

 

NEW QUESTION 90
What are the three phases common across project life cycles?

  • A. Modulation
  • B. Inspiration
  • C. Transition
  • D. Inception
  • E. Construction

Answer: C,D,E

 

NEW QUESTION 91
One of the important changes in the Finance processes in Agile teams is that:

  • A. You will have less oversight over spending as teams are self-organized
  • B. The organization has to be structured around functions like Sales, Development, etc.
  • C. You will not need to monitor cash flows to large extent
  • D. Teams will have a definite budget allocated and will manage to it

Answer: B

 

NEW QUESTION 92
True or False: In a complex adaptive system, it is usually better to have one best practice instead of patterns of good practices

  • A. True
  • B. False

Answer: B

 

NEW QUESTION 93
Which of the following is NOT a tactical scaling factor for a team?

  • A. Organization distribution
  • B. Team size
  • C. Team maturity
  • D. Geographic distribution

Answer: C

 

NEW QUESTION 94
True or False: Any change or improvement in the process is likely to plateau unless efforts are put into constantly reviewing and revising it.

  • A. False
  • B. True

Answer: B

 

NEW QUESTION 95
Which is a supporting role a Disciplined Agile (DA) team?

  • A. Team Lead
  • B. Stakeholder
  • C. Architecture Owner
  • D. Specialist

Answer: D

 

NEW QUESTION 96
......

DASSM Dumps PDF - Want To Pass DASSM Fast: https://exams4sure.actualcollection.com/DASSM-exam-questions.html